March 31, 2013
The old hardwood flooring comes out.
It might have been nice to save it but it was an utter buckled mess.
It was salvaged to grace the floor of a new restaurant in Mahone Bay.


March 15, 2013
We broke up the concrete floor. 3000 square feet of 6" slab! Thankfully there was very little re-bar or mesh so it came out relatively easily.

February 27, 2013
Completely gutted the pub are as well as the addition that will be the service areas and games room
What a mess!
But the building is in amazing shape!